As part of the construction of the WCMUC (West-Central Multi-Use Trail) the city has come up with a design to fix the rail/road crossing at the confluence of the CP tracks, Avenue N and 19th Street. This unsafe crossing situation has led to complaints from both CP and area residents. This is the situation now:
Append-1-Aerial-Map-of-Existing-ConditionsThe city will submit the following design to CP and it will hopefully go before council in 2024 for funding, with a cost estimate a bit under $500k.
Append-4-Proposed-Design-Avenue-N-CP-Rail-CrossingA great plan with benefits for both the immediate community and users of the larger WCMUC path. We’ve also added the full project discussion below.
Avenue-N-CP-Crossing-Report.